Above shows the Silver soldering of the manifold and the seamless joint copper tubing is being completed here. This enables us to remove the 3rd lift scaffold once the pipework has had Nitrogen put in on test and completed. The Nitrogen will also remove any moisture prior to the Refrigerant being put into the system.
To the right the hot water cylinder was completed yesterday along with the return duct from the HRU to the living room. This has enabled us to construct the proposed new airing cupboard which the tenant is looking forward to for additional storage. She has also commented that the old airing cupboard will give her children much needed storage in the 3rd bedroom.
Careful setting out of the base is undertaken here for the Solar Heat Gain Block. It is essential to set it out leaving sufficient area behind, to the sides and front of the proposed SHGB.
To the right a new ceiling goes in the kitchen and plastered.